In geotechnical engineering, soil compaction is the process in which a stress applied to a soil causes densification as air is displaced from the pores between the soil grains. When stress is applied that causes densification due to water (or other liquid) being displaced from between the soil grains then consolidation, not compaction, has occurred. Normally, compaction is the result of heavy machinery compressing the soil, but it can also occur due to the passage of (e.g.) animal feet. In soil science and agronomy, soil compaction is usually a combination of both engineering compaction and consolidation, so may occur due to a lack of water in the soil, the applied stress being internal suction due to water evaporation〔(Soil compaction due to lack of water in soil )〕 as well as due to passage of animal feet. Affected soils become less able to absorb rainfall, thus increasing runoff and erosion. Plants have difficulty in compacted soil because the mineral grains are pressed together, leaving little space for air and water, which are essential for root growth. Burrowing animals also find it a hostile environment, because the denser soil is more difficult to penetrate. The ability of a soil to recover from this type of compaction depends on climate, mineralogy and fauna. Soils with high shrink-swell capacity, such as vertisols, recover quickly from compaction where moisture conditions are variable (dry spells shrink the soil, causing it to crack). But clays which do not crack as they dry cannot recover from compaction on their own unless they host ground-dwelling animals such as earthworms — the Cecil soil series is an example. ==In construction== Soil compaction is a vital part of the construction process. It is used for support of structural entities such as building foundations, roadways, walkways, and earth retaining structures to name a few. For a given soil type certain properties may deem it more or less desirable to perform adequately for a particular circumstance. In general, the preselected soil should have adequate strength, be relatively incompressible so that future settlement is not significant, be stable against volume change as water content or other factors vary, be durable and safe against deterioration, and possess proper permeability. When an area is to be filled or backfilled the soil is placed in layers called lifts. The ability of the first fill layers to be properly compacted will depend on the condition of the natural material being covered. If unsuitable material is left in place and backfilled, it may compress over a long period under the weight of the earth fill, causing settlement cracks in the fill or in any structure supported by the fill. In order to determine if the natural soil will support the first fill layers, an area can be proofrolled. Proofrolling consists of utilizing a piece heavy construction equipment (typically, heavy compaction equipment or hauling equipment) to roll across the fill site and watching for deflections to be revealed. These areas will be indicated by the development of rutting, pumping, or ground weaving. To ensure adequate soil compaction is achieved, project specifications will indicate the required soil density or degree of compaction that must be achieved. These specifications are generally recommended by a geotechnical engineer in a geotechnical engineering report. The soil type - that is, grain-size distributions, shape of the soil grains, specific gravity of soil solids, and amount and type of clay minerals, present - has a great influence on the maximum dry unit weight and optimum moisture content. It also has a great influence on how the materials should be compacted in given situations. Compaction is accomplished by use of heavy equipment. In sands and gravels, the equipment usually vibrates, to cause re-orientation of the soil particles into a denser configuration. In silts and clays, a sheepsfoot roller is frequently used, to create small zones of intense shearing, which drives air out of the soil. Determination of adequate compaction is done by determining the in-situ density of the soil and comparing it to the maximum density determined by a laboratory test. The most commonly used laboratory test is called the Proctor compaction test and there are two different methods in obtaining the maximum density. They are the standard Proctor and modified Proctor tests; the modified Proctor is more commonly used. For small dams, the standard Proctor may still be the reference.〔 While soil under structures and pavements needs to be compacted, it is important after construction to decompact areas to be landscaped so that vegetation can grow. 抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)』 ■ウィキペディアで「Soil compaction」の詳細全文を読む スポンサード リンク
|